Communicating Delays & Blockers ยท Lesson 3 of 3
Unrealistic deadlines
Study notesAbout 3 minutes. A full lesson with quick checks is on its way.
In short
When a deadline looks unrealistic, explain why early, with your assumptions, the risks and some workable options. A quiet yes just delays the problem.
In your work
A client wants a new booking system live in two weeks for their summer programme. You set out what can be ready by then, what it would take to go faster and what could wait for a second phase.
What the UK rules say
- The BCS Code of Conduct says IT professionals must not claim competence they don't have, or misrepresent how products, systems or services will perform.
What to do
- Explain your assumptions and what drives the estimate.
- Name the risks of the current date in plain words.
- Offer options: less scope, more people or a later date.
Watch out for
- Saying yes in the meeting and worrying later.
- Padding estimates silently instead of explaining the risk.
In your organisation
Who agrees delivery dates with clients at your organisation, and how are estimates reviewed?
Your employer's own policies come first.
Sources
- BCS, BCS Code of Conduct (opens in a new tab), checked 6 October 2026.
UK law and guidance, explained for learning. Not legal advice.